Last week’s rain put a real “damper” on our progress! 😞 Nonetheless, our parking lot improvements will continue, with completion still expected in July. Please note the additional changes to previously posted work dates below (with all dates being tentative & weather dependent):
- LOT 10 will be closed for corrective line striping work & installation of the drop off / loading area coating from Wed., June 28 – Wed., July 5
- LOTS 15 & 15A will be closed July 5 – July 12 for seal coat and striping work
- Webber Hall Service Yard will be closed July 12 – 19 for seal coat, stripe, and arrows (sidewalk will also be closed)
All parking lots noted above reference the new lot numbers based on VWCC’s new Campus Map: www.virginiawestern.edu/wp-content/uploads/2023/04/2023-Campus-Map-with-Building-Key-Letter-size.pdf