Numerous parking lot improvements are scheduled for the coming weeks. Please note that the dates below are tentative pending weather events:

  • Lot 14 will be closed May 8-12 for seal coat and stripe
  • Lots 6 & 7 will be closed May 15-26 for mill, pave, patch, seal coat and stripe (if this work runs over, lot 8 will not close until lots 6 & 7 are complete and reopened)
  • Lot 10 will be closed May 26-June 2 for seal coat and stripe
  • Lot 15A will be closed May 29-June 2 for seal coat and stripe
  • Lot 15 will be closed May 29-June 2 for seal coat and stripe
  • Lot 3 will be closed June 5-9 for seal coat and stripe
  • Webber Hall Service Area lot will be closed June 12-16 for seal coat, stripe, and arrows (sidewalk will also be closed)